What changed
Verinode Research · Published Nov 17, 2026California SB 61 (2025) added Civil Code section 8811, which limits retention on contracts for private works of improvement entered into on or after January 1, 2026 to 5% of each payment and 5% of the total contract price. The cap does not apply to residential projects that are not mixed-use and do not exceed four stories, and parties cannot waive it by contract.
Whitmer Law has not written on this change yet
General information, not legal advice. Each change links to its primary source.